1. Navigate to https://dashboard.foreman.mn/dashboard/
2. Navigate to the left navigation bar and click on "Miners"
3. Find the miner that you would like to move to a new client site and click the "Actions" drop down that is associated with that miner
4. Click "Disable" on the drop down
5. Click "Confirm" to disable the miner
6. On the miners page click "Bulk Edit Miners"
7. Click the check box on the miner you are moving
8. Click "Edit "
9. Click the "Choose items to edit for selected miners" field.
10. Scroll down and Click "Client"
11. Click in the "Move Miners to Client" drop down
12. Click on the Client that the miner is moving to. (The Client is associated with the Pickaxe located at the new client site)
13. Click "Apply"
14. Navigate to the left side navigation and click on "Assets"
15. Click on "Bulk Edit" on the Assets Page
16. Select the Asset(s) that would you like to link with the miner(s) being moved to the new client site.
17. Click "Edit"
18. Click the "Choose items to edit for selected assets" field.
19. Click "Client"
20. Click "Location"
21. Click in the "Move Assets to Client" section
22. Select the Client that corresponds with the new client site location of the miner that is being moved.
23. Click "-- Enter or Choose A Location --"
24. Click the location that corresponds with the new location of the miner that is being moved.
25. Click "Apply"
26. Move the miner to the new location
27. Turn on the miner at the new location and confirm that it is connected to the LAN
28. Perform a resync in Pickaxe so the miner is detected at the new location.
- Depending on how you link the miners with assets - Make sure the miner has the correct serial number that was used at the prior location or the correct asset tag that was used at the prior location before it was moved.
The miner should now be enabled and in deployed state at the new client site and the asset should now be linked with the miner that was moved to the new client site.
Comments
0 comments
Article is closed for comments.