Important: CLR is not self-service. CLR and frequency response need a signed contract with an eligible supplier (such as Shell or Priority Power), a CLR-supported RTAC at your site, and setup by Foreman. Contact your Customer Success representative to get started.
A Controllable Load Resource (CLR) is load that can respond automatically to grid frequency. When CLR is set up, Foreman reduces your miners' load when grid frequency drops and brings it back as frequency recovers. This article explains how it works and which settings control it.
How Frequency Response Works
The grid runs at a target frequency (60 Hz in ERCOT and the rest of North America). When demand outpaces supply, frequency falls. With CLR, Foreman watches frequency through your RTAC and responds in near real time:
- Monitor: Foreman reads grid frequency from the RTAC.
- Detect: when frequency moves outside the dead band, frequency response starts.
- Respond: load is reduced in proportion to the deviation, based on the site's droop percentage.
- Recover: as frequency returns to normal, load comes back.
Frequency response is time-sensitive, so the Ramp Down and Ramp Up intervals in your power settings are ignored for these events.
Before You Start
- A contract with an eligible supplier or qualified scheduling entity.
- A CLR-supported RTAC installed and configured at the site.
- Curtailment Opt-in turned on in Settings > Power Control.
- CLR enabled for your account by Foreman. If you don't see CLR Settings, contact Customer Success.
CLR Settings
Go to Settings > Power Control > CLR Settings. Your supplier and Foreman will tell you the values to use.
| Setting | What it does |
|---|---|
| CLR Opt-in | Turns on CLR support. It only takes effect when Dead Band and Droop Percentage are set and a CLR-supported RTAC is configured. |
| Dead Band | How far frequency can move from 60 Hz before frequency response starts. Can't be less than 0. |
| Droop Percentage | The calculated droop for the site, entered as a percent (for example, 5 for 5% droop). Must be between 0 and 100. |
Click Save after making changes.
See When Your Site Responded
Go to Power > Event History to review recent events.
FAQs
Do all my miners have to participate?
No. Talk to Customer Success about limiting participation to load that can be adjusted safely.
Can I turn on CLR without a supplier contract?
No. Without a contract and a CLR-supported RTAC, CLR won't work even if the settings are visible.