Power Controls
Separate Curtailment Retry Values
We've heard that users often prefer continuous retries during a dispatch to ensure miners stay down, but want to limit retries after a dispatch ends so they can resume manual control without disabling curtailment opt-in. To support this, we’ve introduced separate configurable retry durations for curtailment and post-curtailment periods. As part of the rollout, existing configurations will automatically map to the new settings—if a single value was previously set, it will be applied to both “During” and “After.”
-
During Curtailment – Defines how long (in minutes) the system will continue attempting to sleep miners during a curtailment event. Leaving this field empty (
null) will cause miners to be continually slept for the entire duration of the event.Recommended to set to
nullso that the retry occurs throughout the entire event.
-
After Curtailment – Defines how long (in minutes) the system will continue attempting to wake miners once the event ends. Leaving this field empty (
null) will cause miners to be continually woken when not in a curtailment event.ÂRecommended to set in a range of 10-20 minutes after curtailment, or that your retry duration is longer than your ramp settings.Â
Â
To enable Power Controls, please contact the Customer Success team for more information. If you're looking to learn more about Power Controls, check out this article.